Field & cost
Long-lead material: the order date is set by the approval, not by the install date
For the PM or office manager who owns the buyout on a job with fabricated material in it — glass, doors and hardware, steel, millwork, switchgear.
A long-lead item is almost never late because somebody forgot to order it.
It is late because the order could not be placed. The submittal had not come back approved, so there was nothing to release. And the submittal had not come back approved because it went out three weeks after award, or it came back revise and resubmit over one hardware set, or it has been sitting on an architect’s desk since the ninth with nobody counting the days.
By the time anybody notices, the fabricator’s clock has not started. Your install date did not move. The whole delay lands in the last six weeks of your scope, where there is no float left to absorb it.
Our own doors, frames and hardware page states the mechanism in one line: Approval gates a lead time measured in months. Then it shows what that costs you: Nothing ships until the door schedule, the frame schedule, the hardware sets and the keying schedule are approved. One hardware set revised in review can change forty openings, and the order clock starts over.
That is the subject. Not “track your deliveries”. The date that decides whether a fabricated item arrives on time sits four steps upstream of the truck.
Work backwards, because that is the only direction the math runs
Pick the item that is furthest from today and most specific to your job — the curtain wall units, the electrified hardware, the switchgear, the specialty ceiling, the truss package. For each one there are five dates, and usually only the first and the last are written down anywhere.
- Install date. When your crew needs it in the building. This comes off the GC’s schedule, and it moves.
- Delivery date. Install, minus the time the material has to be on site, staged, checked against the schedules and distributed. Rarely zero. On frames and doors it is weeks, because the delivery gets checked against a schedule of four hundred openings before anybody carries one.
- Release for fabrication. Delivery, minus the lead time the fabricator quoted you — and lead time quoted at bid is not lead time on the day you release. Confirm it when you place the order, not when you priced it.
- Submittal approval. Release, minus nothing. On most fabricated material these are the same date: approval is the release. Which means every day of review is a day of your lead time.
- Submittal out the door. Approval, minus the review period in your contract — and minus the resubmittal you should assume you are going to get on at least one package.
Run the subtraction and you land on a date that is usually in the first two weeks of the job, for material that installs in month nine. That is the uncomfortable, correct answer: on a job with long-lead fabrication, buyout is a start-up activity, not something you get to later.
Our low-voltage page says it from the other end of the trade list: the long-lead order that has to go in the week you are awarded.
The three dates worth writing down on day one
Most subs already know their install dates. Almost nobody writes down the two that actually control the outcome.
The date the submittal has to be submitted. Not “early”. A date. It belongs on your start-up checklist next to the preconstruction meeting, because it is the only one of the five you fully control.
The date the submittal has to be approved for the schedule to still work. This is the one that turns a quiet delay into a visible one. If that date passes and you have no approval, you do not have a paperwork problem — you have a schedule problem, and the person who needs to hear about it is the GC’s superintendent, in writing, that week, while it is still a two-week notice and not a nine-month-old excuse.
The date you release the order. Which is also the date your money leaves, and, on many supplier terms, the date a cancellation stops being free. On a custom item, release is the point of no return. Our glazing page puts it in eleven words: Once it is cut it fits one opening on one building.
Those three dates, per long-lead item, on one page, is most of the value. The expediting log a large contractor runs is this, done consistently.
In SubMark: where each of those dates lives
Straight about what holds what, including what does not exist.
The submittal package carries the dates. A package has a submittal number and a revision, a status — draft, submitted, approved, rejected or resubmit required — the party it went to, the date it was submitted, and the date it was approved. There is no required-by field on a package, so the approve-by date from step 4 goes on your own schedule or start-up checklist, somewhere a person will see it pass. A resubmittal is a new revision that keeps its parent, so “we submitted on the 9th and resubmitted on the 6th” survives as two revisions, each with its own submitted date, instead of as somebody’s memory of an email thread. The day it came back is not stamped, so write it down when it lands. We wrote about the log itself in the submittal log.
The purchase order carries the order. A PO belongs to a job and a supplier, and has a PO date, an Expected Delivery date you type, and line items. Its status is Draft, Sent, Invoiced, Paid or Canceled. You can email it to the supplier from SubMark, and push it to QuickBooks with a click, one PO at a time.
Approval before release, if you want it. The PO approval flow is optional and off until you switch it on. With it on, a Draft PO is submitted for approval, somebody holding the approve permission approves or rejects it, and a rejection carries a reason the person who wrote the PO sees on it. On a release that commits six figures to a mill, that reason is the part that earns its keep: it says what to fix before the PO goes back for approval. Resubmitting clears it, so if it will matter later, copy it into the PO notes.
Job costing shows committed next to invoiced. Once the PO is out, the materials line reads as two numbers: materials committed on purchase orders, drawn as its own bar, and what has actually been invoiced. The cost total and the budget alerts use invoiced cost. That distinction matters most on exactly this material, where the commitment is made in month one and the invoice arrives in month seven.
Now the limits, so nothing here is a surprise in the app. Our doors and hardware page answers this on the page itself, and it is the honest version: Procurement is more limited and worth being straight about — there is no expediting dashboard, no lead-time countdown and no vendor acknowledgment tracking. Your purchase orders and the submittal record are where the dates live, and a PO shows committed cost against invoiced cost once the material starts arriving.
Two more worth naming:
- There is no Received status on a purchase order. The five statuses above are the whole list, so “arrived, short two frames” is a note, a daily log entry and a photo — not a state on the order.
- There are no cost codes in SubMark. No library, no import, no mapping. A purchase order goes to the job.
Three habits that do more than any software
Submit before the package is perfect. A submittal that goes out at ninety percent and gets one comment back beats a complete one that goes out four weeks later. The review clock is the long pole, and it does not start until you push.
Confirm lead time at release, in writing, with the quantity. The number you bid in February may not be the number the plant will honor in May. Get the current one on the order acknowledgment, and when it comes back longer than you planned, that is a notice to give the same week rather than a surprise to absorb.
Photograph the delivery and log it the day it lands. Our doors and hardware page describes the delivery stage plainly: product arrives months before it installs, gets checked against the schedules, and gets staged somewhere it will not be damaged or walk off the job. Shortages and transit damage are only recoverable while the truck is fresh in everyone’s memory, and a dated daily log with photos is what does it. A shortage found in month nine is yours no matter who caused it.
The money half, which is a separate argument
All of the above is about dates. There is a second question on the same material: who finances it between the day you pay the mill and the day it is installed.
That is a schedule-of-values question, decided before the job starts. Our glazing page states the stakes: That is a very large amount of cash sitting in a yard or a warehouse, insured and exposed, long before anyone will certify it as installed. It has to be a stored-material line on the schedule of values or it is financed out of your own pocket.
If you are ordering in month one for an install in month nine, read billing stored materials next. The two arguments compound: a long-lead item with no stored-material line is both the thing most likely to be late and the thing most likely to be financed by you.
Submittal review periods, notice requirements, supplier deposit and cancellation terms, and who carries stored material vary, and many subcontracts handle them in a general-conditions attachment rather than in the scope. Your contract governs, and nothing here is legal advice.
What to do this week
Open the job with the longest-lead item on it. Write down three dates for that item: submit by, approved by, release by. Put the “approved by” date somewhere a person will see it pass.
That is the whole discipline. The item that sinks a schedule is almost never the one nobody thought about. It is the one everybody knew about and nobody dated.
See how SubMark protects margin, or what it costs.